Thu 15 May 2008
On Wednesday 14th May we had a meeting with our developers, which happens at the end of each development cycle (typically lasting 2 weeks). At the beginning of this cycle we agreed that basic functionality would be delivered around 2 scenarios covering the web-based user and management interfaces, and the underlying repository technology. These were:
- Finding and printing a known document
- Editing document metadata
The functionality was delivered on Tuesday 14th May and was signed-off by the OARS team at the meeting. The work done so far now provides a base for the next cycle of development, due to be completed on Friday 30th May, followed by a development meeting on Monday 2nd June. The priorities and deliverables for this next cycle were agreed, and briefly are:
- Improved functionality around searching for documents, including use of search results lists
- Improvements to the management interface regarding metadata add/edit
- New functionality for inserting documents into the repository